Enumclaw Pavement Preservation

Project Type

Asphalt

Paving

Location

WA

Owner: City of Enumclaw
Start Date: May 2020
Completion Date: June 2020

The 2020 Pavement Preservation project included 11,600 SY of milling, 1,800 tons of HMA overlay of existing asphalt, concrete removal, 467 LF of concrete curb & gutter, 189 SY of concrete sidewalks, signal loop replacement, minor drainage improvements, 12 ADA ramps, permanent striping and traffic control. The upgrades took place at various locations within the City of Enumclaw.